Project Overview
Installation of new surface water drains to create diversion and upgrade of drainage systems. This was an 18 week programme, working on multiple workfaces in and around the surrounding areas. This included working around live services and under tree canopy – use of Vac Ex where known services are located and working around protected trees.
Project Statistics
- Start Date: January 2025
- Value: £500,000
- Completed: May 2025 (completed 2 weeks early)
- Design of trench and temporary works
- Controlled management of ground and surface water off site
- Working on live roads under traffic management.